Applied Digital Brings an Additional 75 MW of AI Infrastructure Online at Polaris Forge 1
Applied Digital said Ready for Service for the second phase of Building 2 at Polaris Forge 1 in Ellendale, North Dakota, adding 75 MW of critical IT load across three 25 MW data halls. The Oct. 2, 2026 milestone completes Building 2’s 150 MW and lifts operational campus IT load to 250 MW toward a fully leased 400 MW AI Factory buildout. The company designs and operates purpose-built HPC and AI data centers.