TeraWulf Expands Contracted Power Capacity at its Muskie Data Campus to 1 GW

5 Oct 2026

Released by TeraWulf

MediaRelease.co Summary

TeraWulf has signed an amended electric service agreement with Kentucky Power that doubles contracted power at its Muskie Data Campus in eastern Kentucky from 500 MW to 1 GW. The second 500 MW phase moves forward from 2030 to 2029, subject to regulatory approval, while the first phase is still targeted to begin ramping in 2028. Kentucky Power is building a 765-kV/345-kV substation to serve the AI and high-performance computing campus.

Original release

Amended Kentucky Power agreement advances the second 500 MW phase into 2029 amid strong customer interest

EASTON, Md., Oct. 05, 2026 – TeraWulf Inc. (Nasdaq: WULF) (“TeraWulf” or the “Company”), a vertically integrated owner, developer and operator of large-scale digital infrastructure, today announced that it has executed an amended and restated electric service agreement with Kentucky Power, an American Electric Power (“AEP”) company, increasing contracted power capacity at its Muskie Data Campus in eastern Kentucky from 500 megawatts (“MW”) to 1 gigawatt (“GW”).

The amendment advances planned delivery of Muskie’s second 500 MW phase from 2030 to 2029, subject to Kentucky Public Service Commission approval and Kentucky Power’s construction schedule. Development will proceed consistent with the requirements of Governor Beshear’s Executive Order on Data Center Development (2026-494). The first 500 MW phase remains targeted to begin ramping in 2028.

“Customer interest in Muskie has been tremendous, and power availability is central to those conversations,” said Paul Prager, Chairman and Chief Executive Officer of TeraWulf. “Securing the next 500 MW and moving its planned delivery into 2029 gives us greater flexibility to meet prospective customers’ deployment needs. It also builds on the progress our teams have made with Kentucky Power since we acquired the site.” Additionally, the Company continues to evaluate the campus’s potential to support up to 2 GW over time, subject to additional utility planning, infrastructure and agreements.

TeraWulf acquired Muskie in May 2026 for phased development as an AI and high-performance computing campus. Kentucky Power is developing a 765-kV / 345-kV substation connected to the regional transmission network to serve the site.

The Muskie amendment follows TeraWulf’s approach to large-scale development in Kentucky: coordinate with the utility on the infrastructure needed to serve the campus, provide financial protections for utility investment and structure the agreement to benefit existing customers. In August, the Kentucky Public Service Commission approved the separate electric service agreement for TeraWulf’s Justified Data Campus in Hawesville, finding that its terms adequately protected existing customers and appropriately allocated the costs and risks of serving that project.

About TeraWulf

TeraWulf develops, owns and operates large-scale, power-backed digital infrastructure in the United States, purpose-built for high-performance computing and artificial intelligence workloads. The Company operates the Lake Mariner Data Campus in New York and is developing and pursuing additional large-scale campuses in Kentucky, New York and Maryland.

Source: https://investors.terawulf.com/news-events/press-releases/detail/146/terawulf-expands-contracted-power-capacity-at-its-muskie-data-campus-to-1-gw

Key details

Issued by
TeraWulf
Published
5 Oct 2026
Publisher country
United States
Topics
Data Center

Source: https://investors.terawulf.com/news-events/press-releases/detail/146/terawulf-expands-contracted-power-capacity-at-its-muskie-data-campus-to-1-gw

MediaRelease.co ID: mr02239 · Markdown

← Back to Data Center overview