Recognized First HPC Lease Revenue
Expanded Barber Lake Lease Term to 20 Years, Increasing Contracted Revenue to $9.1 Billion
Received Conditional Base Load Classification for Colchis (1 GW)
Began Development of Lateral Pipelines to Facilitate up to 2.5 GW of On-Site Generation for Data Center Expansion
NEW YORK, Nov. 02, 2026 (GLOBE NEWSWIRE) -- Cipher Digital Inc. (NASDAQ: CIFR) (“Cipher” or the “Company”), a leading developer, owner, and operator of industrial-scale data centers, today announced its third quarter 2026 financial results, with an update on its operations and business strategy.
The third quarter marked a milestone in Cipher’s transition to a leading HPC development platform, as the Company recognized its first HPC lease revenue following rent commencement at Black Pearl. Across Black Pearl and Barber Lake, multiple data halls are scheduled to come online through year-end.
Cipher also highlighted its previously announced amendment to the Barber Lake lease, which adds a second 10-year term directly with a leading AI lab. The amendment increases total contracted revenue at the site to approximately $9.1 billion, adding approximately $5.2 billion of incremental rent. It also establishes a phased delivery schedule aligned with the tenant’s compute deployment, and construction remains on track to deliver against the amended schedule.
In the third quarter, the Company received conditional classifications across several pipeline sites through ERCOT’s Batch Zero process, including a conditional base load classification for 1 GW at Colchis and conditional studied load classifications with Provisional Controllable Load Resource (“PCLR”) designations for an additional 1.6 GW.
The Company also commenced development of lateral natural gas pipelines capable of supporting up to 2.5 GW of on-site generation, and acquired Horizon, a 70 MW site in Texas expected to energize in 2029. The pipeline also includes 270 MW of capacity available in 2027, for which the Company continues to advance tenant discussions and design work. Cipher’s development pipeline today totals approximately 5.9 GW.
“Cipher was built for this market, and this quarter we took important steps to strengthen our position for the long term,” said Tyler Page, Chief Executive Officer. “The decisions we made early on about who we partner with, how we structure our projects, how we navigate a dynamic regulatory environment and how we engage with our communities were made for exactly these conditions. Demand for compute is growing, and our relationships with leading hyperscalers and AI labs are deepening. We are adding new capacity to our pipeline, investing earlier in every project and advancing design work before committing to new leases, so we are well positioned for our next phase of growth.”
Finance and Operations Highlights
Recognized first HPC lease revenue
Delivered first capacity at Black Pearl with additional capacity across all three campuses expected to come online in phases over the coming months
Expanded the Barber Lake lease to a 20-year term, increasing total contracted revenue at the site to approximately $9.1 billion
Acquired Horizon, a 70 MW Site in Texas with energization expected in 2029
Completed an $850 million offering of 0.000% convertible senior notes due 2032, funding additional equity investment into Barber Lake in connection with the lease expansion, with associated capped call transactions raising the effective conversion price to $28.35 per share
Equitized approximately $165.9 million of the 1.750% convertible notes due 2030, retiring more than 90% of those notes
Received a conditional base load classification for 1 GW and conditional studied load classifications for 1.6 GW with PCLR designations, through ERCOT’s Batch Zero process
Commenced development of lateral pipelines to support up to 2.5 GW of potential on-site generation across multiple sites
Barber Lake data center construction on track to meet the amended milestones
Black Pearl data center continues to progress towards completion with ongoing equipment installation and energization across various data halls
Stingray construction advancing, with steel erection progressing on schedule and shell construction expected to be completed in the fourth quarter
Q3 2026 Revenue of $27 million and Adjusted EBITDA of negative $10 million